Entry Point Projects (EPPs) GNI  million Job Private Investment
(RM million)
Public Investment
(RM million)
1 National Seaweed Nucleus 420 13,788 359 182
2 Sabah Agro Industrial Precint (SAIP) 195 399 584 94
3 Taman Kekal Pengeluaran Makanan (TKPM) 35 479 13 47
4 Integrated Marine Fish Culture 710 1,981 804 21
5 Swiflet Commercial Centre (SCC) 405 7,648 167 13
6 High Finned Grouper & Barramundi 995 760 118 32
7 Integrated Shrimp Aquaculture 267 3,626 716 48
8 Sea Cucumber & Tiger Grouper Combine Culture 555 930 100 41

Total

3,582 29,611 2,861 478

EPP 1 : NATIONAL SEAWEED NUCLEUS of Malaysia
EPP 2 : SABAH AGRO INDUSTRIAL PRECINT (SAIP)
EPP 3 : TAMAN KEKAL PENGELUARAN MAKANAN (TKPM)
EPP 4 : INTEGRATED MARINE FISH CULTURE
Coconut  | Coffee  | Rubber  |  Tongkat Ali  |  FRESH MARKET OF KUNDASANG  |  VEGETABLE  |  SABAH FOOD PARK 
FRUITS OF SABAH  |  What to eat in Tawau  |  TREES  | 

 

 

Taman-TKPM

EPP 3 : TAMAN KEKAL PENGELUARAN MAKANAN (TKPM)


Key outcomes of the EPP

   
Increase Fresh Fruit Export :
A) Papaya- 63,855 mt [355 ha] @ 7 years
B) Jackfruit- 12,237.5 mt [725 ha] @ 5 years
Future opportunity for pineapple, star fruit and banana
Job opportunity: 3,184 people [until 2020]
To Develop new local agropreneur: 66
Generate Revenue for the State Government through land rental- RM3,538,000 .00 until 2020
   
 

What needs to be done?

 
  Need funding for basic infrastructure (road, water supply and electricity) need to be construced in order for the TKPM to be implement.
The anchor company should be able to export the farm produce directly to the importing country/ client through Sabah Port [Sandakan] to shorten the travelling time rather than through Port Klang.
 
 

Key Challenges

 
  Illegal squatters
No basic infrastructure
 
   

Mitigation Plan

    District Officer could issue Eviction Notice to the illegal squatter with the assistance from the Land & Survey Department ,Police , District Surveyor and District Council [Enforcement Officer]
To construct access road from Sandakan- Lahad Datu Highway to the TKPM site.
To provide water supply and reservoir [pond] for water collection.
To provide power connection [SESB] and standby generator.

1 - TKPM MANDALIP AU (517 HA)

Background Of The Project TKPM Mandalipau, Papar.
The site is situated 25 km from Papar Town.
Overall area = 517 hectares
Acreage developed = 517 hectares (3 Phase)
Gazette for TKPM = year 2006; GN 78-2006
In 2009 listed under the Sabah Development Corridors (SDC).
Current status- The final report on Design Plan (Preliminary Report) done by SABA Perunding S/B costing RM860,580.00 > SDC

2 - TKPM SG. LOKAN (700 HA)

Background Of The Project TKPM Sg. Lokan
The site is situated 80 km from the Kinabatangan District , Sandakan City.
Overall area = 732.48 hectares
1st Phase Develop = 400 hectares
2nd. Phase Develop = 300 hectares
Gazette for TKPM = year 2005; GN 345-2005
In 2009 listed under the Sabah Development Corridors (SDC).
Current Status- The final report on Design Plan (Preliminary Report) done by PY Konsep Perunding costing RM389,120.00 > SDC

TKPM, Sg. Lokan, Plot Design


3 - TKPM SG. KOYAH (80 HA)

Background Of The Project TKPM Sg. Koyah
The site is situated 52 km from the Kinabatangan District, Lahad Datu town
Overall area = 80 hectares
Acreage developed = 80 hectares
Gazette for TKPM = year 2004; GN 47-2004
In 2009 listed under the Sabah Development Corridors (SDC).
Current status- The final report on Design Plan (Preliminary Report) done by SARG Konsult S/B costing RM308,600.00 > SDC


Categorized under EPP 7 [Fruit & Vegetable]
To alienate land permanently for tropical fruits production.
To give opportunity for private sector to be involved in fruits production
To give opportunity for local agropreneur to be involved in food crops production.
Anchor Vendor Concept.
Strengths of the Food crops sector:
- Food security
- BOT, Import vegetable & fruits higher than export
- Food crisis
- Geographical location of Sabah closer to Taiwan, Japan, Brunei (EAGA) and Korea
- Sabah still lacking in food crops agropreneur
- High demand of tropical fruits overseas
Production: Low vegetable & fruits exported, ( 1,487 mt /RM3.8 million (statistic 2008)
Distribution : Project focus to east coast Sabah (Div. Sandakan and Tawau), to softened the effect of vast expansion of Palm oil plantation (estimated acreage of palm oil plantation is over 93% cultivated on arable, suitable and fertile agri land (Agri statistics bulletin 2007.