1 - Lahad Datu Regas Terminal
EPP 1 : LAHAD DATU REGASIFICATION TERMINAL (LD RGT)
| To develop a facilities to receive, store and vaporize imported LNG with a maximum capacity of 0.76 MTPA (up to 100 mmscfd) and supply the natural gas to the Power Plant | |
|
| Key outcomes of the EPP / KPIs |
| • Availability of natural gas supply at east
coast of Sabah including Sandakan, Lahad Datu and Tawau (also along
the route) • Transfer of technology and knowledge to local manpower and contractors who are involved with this project • Spurring the economy along the pipeline |
| Key Challenges |
| • Transporting major equipment and bulk materials from Sandakan
to Lahad Datu (~200km) • Shortage of capable manpower due to simultaneous construction of LD power plant • Available manpower are lack of re-gas terminal construction skills (special) • Potential security threat with historical events of pirates attack towards workers and equipment • Coordination for safety and evacuation during emergency with local authorities |
| What needs to be done? |
| • Construction period of LNG Storage Tank which is the critical
path of the project (normally will take up to 24 months) • Front End phase of a project, where activities are mainly focused towards project planning and contracting/bidding activities for the appointment of Frond End Engineering Design Consultant expected in mid-October 2011 • Evaluate and finalize the land lease of the reclaimed land of the proposed site with POIC. • Site Reclamation works is expected to start by Q1 2012 |
| Mitigation Plan |
| • Improvement of the road condition from Sandakan to Lahad Datu
or consider for permanent/temporary jetty at Lahad Datu • Proper education planning to prepare and develop the skilled and semi skilled manpower • Collaboration with state authorities to tighten the security along the coast lines |
|