5 - Lahad Datu Power Plant (300MW)
EPP 5 : LAHAD DATU POWER PLANT (300MW)
| The fuel for the power
plant will be LNG The power plant and LNG re-gasification plant are to be built in POIC Lahad Datu Phase 3 |
|
| Key outcomes of the EPP / KPIs |
| • Creation of 390 jobs for Sabahan from top management to
supporting staff during operations and 2737 jobs during
construction. Hence, transfer of technology and knowledge will take place to local manpower and contractors • Additional 300 MW of cleaner and stable energy supply into SESB to preserve Sabah eco treasure • Reduce the yearly lost from industrial losses RM4.59billion/per year due to power interruption |
| Key Challenges |
| • POIC policy not to sell sea front land and project owner plan
to purchase the land for jetty and port to lower the project cost
and ensure the security of long term investment • POIC policy for them to build and operate the jetty vs project owner plan to self build and self operate the jetty to reduce cost • Lengthy negotiation period on Power Purchase Agreement (PPA) • Shortage of capable manpower and local contractors |
| What needs to be done? |
| • Project consortium needs to Resolve land purchase/lease
matters by Dec 2011 • Resolve jetty building and ownership matters between project consortium and POIC / Sabah Authorities by Dec 2011 • Project consortium needs to start the land works latest by Q1 2012 • MLNG needs to secure the LNG import supplies from international market by 2014 |
| Mitigation Plan |
| • Work on the agreed price for both parties whether on
selling/purchasing or leasing the land • Speed up state government decision on the ownership of the jetty • Intervention from MPRC, state government into the negotiation of PPA to speed up the decision • Proper education planning to prepare and develop the skilled and semi skilled manpower |
|